Curtailment risk imminent for Indian solar projects in the years to come

18 May 2016 |

With a target of 100 GW, India is hoping to get 8% of its power requirements from solar PV by 2022. In comparison, Germany got around 7.5%[1] of its power consumption from solar PV in 2015 and China is still at around 3%[2]. In Germany, where most of the solar capacity has been deployed in the form of distributed solar projects, billions of Euros are being spent on grid projects to help reduce curtailment in green power. Despite that, according to a government report[3], Germany curtailed about 1,581 gigawatt-hours of green energy in 2014, a threefold increase over the previous year. In China, grid curtailment issues continue to impact the export of power from solar projects and some provinces such as Gansu (31%) and Xinjiang (26%) have been hit particularly badly[4].

In Germany, on sunny weekdays, solar power can cover 35 percent of the momentary electricity demand. On weekends and holidays this ratio goes up to 50 percent and sometimes even higher. At such times, power pricing gets distorted, renewable and other sources of generation often need to be backed down. These problems are occurring despite Germany’s peak daily demand hours coinciding with peak solar generating hours. An integrated European grid, smarter grid management and abundant availability of dispatchable gas based power comes in handy at such times.

India is not as lucky as it is an evening peak country and dispatchable sources of power are limited resulting in much higher risk of curtailment for solar power. This risk is not too far out into the future as many states are expected to achieve significant grid penetration in the next 1-2 years. Telangana is expected to add around 3 GW of solar power capacity by 2017 and the state is known to be planning further significant allocations. With average estimated day time demand of 6 GW in 2017, 50% of the state’s daytime demand is likely to be met from solar power.

Karnataka and Andhra Pradesh are likely to face similar issues. But the most extreme case is Jharkhand where the average day time power demand is less than 1 GW but the state has already tendered 1.2 GW of solar projects. The government is planning upgradation of transmission infrastructure through its green corridor program but such projects can typically take up to five years to become operational. In comparison, solar projects become operational within 12-18 months. States with such high solar penetration are therefore expected to face significant grid curtailment.  But Indian solar project developers typically assume that they will maintain uptime of 99% or more for a period of 25 years.

BRIDGE TO INDIA believes that the future risk of curtailment of power due to grid congestion especially in high renewable penetration areas, can upset project cash flows and return expectations. In an aggressive bidding scenario, developers may not be appropriately pricing in such risks.

Curtailment risk could have a substantial negative impact on the investment climate for the sector in the years to come. The government needs to prioritize investments into the transmission infrastructure to proactively assuage concerns of the sector.

[1] https://www.ise.fraunhofer.de/en/publications/veroeffentlichungen-pdf-dateien-en/studien-und-konzeptpapiere/recent-facts-about-photovoltaics-in-germany.pdf

[2] http://www.economist.com/news/business/21696941-solar-power-reshaping-energy-production-developing-world-follow-sun

[3]http://www.bundesnetzagentur.de/SharedDocs/Downloads/EN/BNetzA/PressSection/ReportsPublications/2015/Monitoring_Report_2015_Korr.pdf?__blob=publicationFile&v=4

[4] http://www.pv-tech.org/news/china-displaces-germany-as-solar-capacity-leader


Recent reports

India PV Module Intelligence Brief – Q1 2022   

This report captures quarterly trends in module demand and supply, import and domestic production volumes, supplier market shares, break-up by technol...

Buy Report

India Corporate Renewable Brief | Q1 2022   

Our latest edition of quarterly report provides a detailed regular update on key trends and developments in the C&I renewable market....

Buy Report Download Executive Summary

India Solar Compass Q1 2022   

This report provides a detailed update of all key sector developments and trends in the quarter – capacity addition, leading players, tenders and po...

Buy Report Download Executive Summary

Technical Standards For Balance of Systems In Solar Projects

India’s solar capacity has grown from just 10.5 GW to 52 GW in the last five years and the country has adopted ambitious target of building 280 GW s...

Download

India PV Module Intelligence Brief – Q4 2021   

BRIDGE TO INDIA has released a new quarterly report, India PV Module Intelligence Brief, capturing ongoing demand-supply, pricing, technology and poli...

Buy Report

Solar pumps – waiting to take off   

The government has set a target to install 2 million off-grid and 0.75 million grid connected agricultural solar pumps by FY 2023. However, progress h...

Buy Report Download Executive Summary
Award winnig research
We use cookies to offer you an optimal user experience and collect information on website usage.