MSEDCL recently concluded auction for its 250 MW peak power tender issued in August 2022. Tariff for daytime power (10 AM-6 PM) was fixed at INR 2.42/ kWh and bidders were required to quote a tariff for supply during remaining hours (6 PM-10 AM). There were four bidders...
MSEDCL recently concluded auction for its 250 MW peak power tender issued in August 2022. Tariff for daytime power (10 AM-6 PM) was fixed at INR 2.42/ kWh and bidders were required to quote a tariff for supply during remaining hours (6 PM-10 AM). There were four bidders...
CERC, the central power sector regulator, has issued an order capping base penalty rate under Deviation Settlement Mechanism (DSM) at INR 12/ kWh for both power producers and consumers. Earlier, the base rate was set at maximum of weighted average price discovered on power exchanges and weighted average ancillary service charge...
CERC, the central power sector regulator, has issued an order capping base penalty rate under Deviation Settlement Mechanism (DSM) at INR 12/ kWh for both power producers and consumers. Earlier, the base rate was set at maximum of weighted average price discovered on power exchanges and weighted average ancillary service charge...
MNRE has finally released the much-anticipated National Green Hydrogen Mission document. As expected, the target is to build 5 MMTPA green hydrogen production capacity fuelled by 125 GW renewable power capacity by FY 2030 for domestic consumption. The document sets out an additional aspiration of becoming a global hydrogen hub with another 10 MMTPA capacity by FY 2030 for exports...
MNRE has finally released the much-anticipated National Green Hydrogen Mission document. As expected, the target is to build 5 MMTPA green hydrogen production capacity fuelled by 125 GW renewable power capacity by FY 2030 for domestic consumption. The document sets out an additional aspiration of becoming a global hydrogen hub with another 10 MMTPA capacity by FY 2030 for exports...
Best wishes for a very happy new year to all our subscribers! 2022 was the year when renewable power sector proved its resilience in the face of extreme cost pressures, BCD, ALMM, shortage of modules and transmission system hold ups. Our early estimates suggest a record capacity addition of 18.8 GW, up 50% YOY, with a split of 90:10 between…
Best wishes for a very happy new year to all our subscribers! 2022 was the year when renewable power sector proved its resilience in the face of extreme cost pressures, BCD, ALMM, shortage of modules and transmission system hold ups. Our early estimates suggest a record capacity addition of 18.8 GW, up 50% YOY, with a split of 90:10 between…
India’s corporate renewable market is becoming more vibrant with strong demand, policy and technology levers. Driven by net zero targets and investor mandates, corporate consumer...
Buy Report Download Executive SummaryGreen hydrogen is a versatile fuel which may be used as an energy store, fuel and feedstock across multiple sectors. Refining and fertiliser industries are expected to be early ado...
Buy Report Download Executive SummaryThis report captures quarterly trends in module demand and supply, import and domestic production volumes, supplier market shares, break-up by technology and rating, pricing trends...
Buy Report Download Executive SummaryThis video presents a summary of major sector developments including tender issuance, auctions, policy and regulatory developments, financial deals and related market trends in November 2022.
This video presents a summary of major sector developments including tender issuance, auctions, policy and regulatory developments, financial deals and related market trends in November 2022.
India added 3,761 MW corporate renewable capacity in first nine months of the year, 61% more than in whole of 2021. The numbers are especially pleasing because of a series of recent adverse developments including increase in construction costs, imposition of BCD and ALMM, and high policy uncertainty....
India added 3,761 MW corporate renewable capacity in first nine months of the year, 61% more than in whole of 2021. The numbers are especially pleasing because of a series of recent adverse developments including increase in construction costs, imposition of BCD and ALMM, and high policy uncertainty....
2022 was an exceptional year in terms of project auctions. There was a double whammy for project developers as they were hit by weak demand from DISCOMs and escalating costs. Total auctioned capacity fell by 47% over previous year to just 9,855 MW, a five year low. There were only 3 auctions over 100 MW between all central government entities…
2022 was an exceptional year in terms of project auctions. There was a double whammy for project developers as they were hit by weak demand from DISCOMs and escalating costs. Total auctioned capacity fell by 47% over previous year to just 9,855 MW, a five year low. There were only 3 auctions over 100 MW between all central government entities…
Amongst all the travails including land, transmission, cost pressures, delays in equipment supply and policy uncertainty, financing continued to be somewhat of a bright spot for the renewable sector in 2022. The year saw as many as 18 equity investment deals totalling at least USD 3,873 million, up 79% over 2021...
Amongst all the travails including land, transmission, cost pressures, delays in equipment supply and policy uncertainty, financing continued to be somewhat of a bright spot for the renewable sector in 2022. The year saw as many as 18 equity investment deals totalling at least USD 3,873 million, up 79% over 2021...
This video presents a summary of major sector developments including tender issuance, auctions, policy and regulatory developments, financial deals and related market trends in October 2022.
This video presents a summary of major sector developments including tender issuance, auctions, policy and regulatory developments, financial deals and related market trends in October 2022.
In a recent note, we identified land, transmission and technology as the most acute supply side challenges for the renewable sector. Dependence on overseas technology is a key risk specifically for the Indian renewable sector. However, technology receives little attention in the discourse on sector dynamics...
In a recent note, we identified land, transmission and technology as the most acute supply side challenges for the renewable sector. Dependence on overseas technology is a key risk specifically for the Indian renewable sector. However, technology receives little attention in the discourse on sector dynamics...
The central government has issued a total of 139 policies and related amendments in the last five years. That number could be multiplied by about 25x to account for multiplicity of bodies including state governments, regulators, nodal agencies and DISCOMs to understand magnitude of policy...
The central government has issued a total of 139 policies and related amendments in the last five years. That number could be multiplied by about 25x to account for multiplicity of bodies including state governments, regulators, nodal agencies and DISCOMs to understand magnitude of policy...
Of the four main supply side factors for renewables – land, transmission, technology and financing, the first two are the most critical – always in short supply and on critical time path due to long lead times, complex regulations and increasing cost. Despite multiple government initiatives including solar parks, green energy corridors and renewable energy zones...
Of the four main supply side factors for renewables – land, transmission, technology and financing, the first two are the most critical – always in short supply and on critical time path due to long lead times, complex regulations and increasing cost. Despite multiple government initiatives including solar parks, green energy corridors and renewable energy zones...