Last week, Solar Energy Corporation of India’s (SECI) 750 MW utility scale auction in Bhadla solar park saw tariffs fall to a new astounding low of INR 2.44 (US¢ 3.79)/ kWh. This comes after much brouhaha over tariffs falling to INR 3.25/ kWh (levelized) and INR 3.15/ kWh in Rewa, Madhya Pradesh and Kadapa, Andhra Pradesh respectively in the last three months. At the same time last year, tariffs for most tenders were observed around INR 4.60 (US¢ 7.1)/kWh mark. What explains a tariff reduction of almost 50% in one year or 25% in just three months?

Winning bidders for the two tenders in Bhadla include ACME (INR 2.44/kWh, 200 MW), Softbank (INR 2.45/kWh, 300 MW), Phelan (INR 2.62/kWh, 50 MW), Avaada (INR 2.62/kWh, 100 MW) and Softbank (INR 2.63/kWh, 100 MW).

A key obvious contributor to falling tariffs is sharp reduction in module prices, down almost 30% in the last one year. And developers seem to be pricing in similar price reduction going forward – at about US ¢ 23/Wp in the next 10 months. Although module industry dynamics remain benign, it seems a very bold call to price such reduction in base case.

Fall in Indian debt cost by up to 1.00% per annum over the last year (equivalent to tariff reduction of approximately INR 0.10/ kWh), higher irradiation in Bhadla (INR 0.15/ kWh), lower solar park charges (INR 0.05/ kWh) and stronger Rupee go some way in explaining the tariff reduction. Another relevant factor is improvement in SECI’s credit rating. The participating bidders’ list in Bhadla tender shows that both Indian and international developers are growing comfortable with SECI offtake risk.

But the other very important factor is increased competition amongst developers due to fewer new tenders and complete lack of pipeline visibility over the next year. We have maintained for some time that the Indian solar market is getting overheated and that these tariffs are unsustainable.

Falling tariffs are a double-edged sword for the sector. They make solar power more attractive for consumers but are also making investors and lenders jittery. In the near term, they are also creating uncertainty in the minds of policy makers and creating new risks for older projects auctioned at 2-3x higher tariffs.


Recent reports

India Corporate Renewable Brief | Q2 2021

Our latest edition of quarterly report provides a detailed regular update on key trends and developments in the C&I renewable market....

Download

India Renewable Map | June 2021

India’s total utility scale solar and wind capacity reached 77,082 MW by 30 June 2021. New capacity addition in the last 12 months was 6,530 MW, up ...

Download

India Solar Compass Q2 2021   

This report provides a detailed update of all key sector developments and trends in the quarter – capacity addition, leading players, tender and pol...

Buy Report Download Executive Summary

India Corporate Renewable Brief | Q1 2021

Our new quarterly report provides a detailed regular update on key trends and developments in the C&I renewable market....

Download

India Renewable Power CEO Survey | 2021

The India Renewable Power CEO Survey provides a glimpse into key trends of the industry that affect important management decision-making by business l...

Download

Wind solar hybrid projects   

India’s wind solar hybrid (WSH) project capacity is poised to grow from 310 MW at present to about 9,500 MW by 2025....

Buy Report Download Executive Summary
Award winnig research
We use cookies to offer you an optimal user experience and collect information on website usage.