Weekly Update: A Lesson from Bihar: states should allocate solar projects based on a policy

02 July 2013 | Jasmeet Khurana

Bihar State Power (Holding) Company Limited (BSPHCL) had recently issued a tender for an allocation of a 100 MW capacity in the state. Today (July 1st 2013), is the last date for the submission of the bids. The solar projects are expected to meet the solar renewable purchase obligations (RPOs) of the state-owned power distribution companies. Allocation of projects should be under a policy...

Read more...


Weekly Update: New allocations in India for the current financial year to reach 2.5 GW

18 June 2013 | Jasmeet Khurana

Andhra Pradesh, Tamil Nadu, Uttar Pradesh and Punjab have all recently issued Letters of Interest (LOIs) after carrying out their respective processes for allocation of new solar PV projects. These allocations would cumulatively account for a capacity of almost 1.5 GW. Andhra Pradesh is now looking to allocate a solar PV capacity of 350 MW and not 1000 MW, while Uttar Pradesh planned to...

Read more...


Weekly Update: Market for sale of solar power to commercial and industrial consumers picks up

05 June 2013 | Jasmeet Khurana

We observe a trend in the Indian solar PV project development space towards bilateral, open access, contracts (often under the ‘group captive’ model) for sale of power to industrial consumers. Many project developers are keen on the market for bilateral sale of power, while some are already selling power directly to industrial consumers Project developers plan for only a portion of...

Read more...


Weekly Update: Penalties for CSP projects likely to be deferred by 10 months as no project is ready for timely commissioning

14 May 2013 | Jasmeet Khurana

The Ministry of New and Renewable Energy (MNRE) has decided to defer the penalties that are to be levied on delayed solar thermal (CSP) projects. 470 MW were allocated under phase one of the National Solar Mission (NSM) in December 2010 and were to be commissioned in May 2013. However, none of the projects are expected to meet this deadline. No project is expected to reach completion before...

Read more...


Weekly Update: SECI launches the second round of competitive bidding for rooftop solar PV projects

07 May 2013 | Jasmeet Khurana

The Solar Energy Corporation of India (SECI) has announced the second round of biddings for the implementation of large scale, grid connected rooftop PV systems ranging from 100 kWp to 500 kWp for a total allocation of 11.1 MW. A developer can apply for multiple projects for a minimum allocation of 250kWp and a maximum of 2 MWp No Feed-in-Tariff is being offered. Instead, the bidder will...

Read more...


Weekly Update: Andhra Pradesh changes allocation process, policy instability to hurt investor confidence

30 April 2013 | Jasmeet Khurana

The south Indian state of Andhra Pradesh had carried out a bidding process for an allocation of 1,000 MW earlier this year. The state followed a L1 (lowest bid) process, where developers were required to meet the lowest tariff being offered by any other developer for a given sub-station. The policy’s bidding process accounted for different project sizes, land costs and irradiation levels...

Read more...


Weekly Update: Clarification on projects commissioned under batch two phase one of the NSM

09 April 2013 | Jasmeet Khurana

Last week in our April 2013 edition of the India Solar Compass we had mentioned that a number of projects under the Batch II, Phase I of the NSM had not been commissioned within the deadline of February 26th 2013. Since then, we have had a chance to interact with some company representatives and market stakeholders and would like to clarify that a few of these project have in fact been...