The big event in 2019 is obviously the general elections. As policy purdah looms, politics is likely to dominate over reforms and concrete action for most of the year. But we don’t expect any retreat in push for RE irrespective of who comes to power. We expect a total RE capacity addition of 15,860 MW in 2019, a sharp jump of 50% over 2018. More than 69% of capacity addition is expected to come from utility scale solar projects.

Figure 1: Total RE capacity addition in 2019, MW

Source: BRIDGE TO INDIA research

Total domestic module manufacturing volume is expected to remain at about 3,000 MW. We should see greater adoption of new technologies such as mono-type modules, micro inverters, storage (finally expected to start rolling with likely announcement of a National Storage Mission).

Our estimate for utility scale solar EPC cost by year-end is INR 26/ Wp. Tariffs are likely to stay range bound within INR 2.50-3.00/ kWh depending on project location and offtake risk profile.


Recent reports

India Solar Compass Q3 2020   

India added just 351 MW of solar power generation capacity in Q2 2020 taking total installed capacity to 38,377 MW by 30 June 2020....

Buy Report Download Executive Summary

Solar Manufacturing Prospects   

Buoyed by government promises of customs duty on imports and financial incentives, solar manufacturing sector is witnessing renewed interest....

Buy Report Download Executive Summary

India Solar Rooftop Map | June 2020

India’s operational rooftop solar capacity reached 5,953 MW as on 30 June 2020. Only 1,140 MW capacity is estimated to have been added in the twelve...

Download

India Renewable Map | June 2020

India’s utility scale solar and wind capacity reached 69,808 MW as on 30 June 2020. Only 6,284 MW of new capacity was added over last 12 months, dow...

Download

India Solar Compass Q2 2020   

India added just 351 MW of solar power generation capacity in Q2 2020 taking total installed capacity to 38,377 MW by 30 June 2020....

Buy Report Download Executive Summary

Transmission planning, implementation and status   

Transmission remains a critical bottleneck to growth of India’s renewable power sector....