Sharp rise in peak power deficit

14 March 2022 |

It is early March and peak power demand this month has already hit 195 GW as against 186 GW last year. Peak demand over last five years has grown at a CAGR of 4.6% outpacing total power demand CAGR of 3.4%.

Figure 1: Peak and total power demand

Source: CEA, BRIDGE TO INDIA research

These are official peak demand numbers reported by CEA, which also reports a rising peak deficit of 2.9 GW in the current financial year as against a deficit of about 1.4 GW in the last 3-4 years. Actual peak deficit is almost certainly much higher as DISCOMs routinely resort to load-shedding in response to rising demand. Increasing peak demand has led to greater volatility in hourly prices in the day-ahead-market on the exchanges. Morning and evening peak power prices are now routinely hitting and crossing INR 8/ kWh as shown in the following chart. Indeed, the day-ahead prices touched a new high of INR 20/ kWh on 4 March 2022.

Figure 2: Average hourly prices in the day-ahead market, INR/ kWh

Source: Indian Energy Exchange, BRIDGE TO INDIA research

There has been a similar increase in round-the-clock (RTC) prices on the exchanges over last 5 years. RTC prices in first week of March 2022 touched INR 5.41/ kWh against INR 4.07 and 2.46 seen one and two years earlier respectively.

There are several factors explaining demand-supply imbalance and price spikes. Growth of renewable capacity, concomitant with the sharp slowdown in thermal capacity addition over the last few years, is the biggest factor at play. Surplus power available for sale on the exchanges has almost completely dried up. Imported coal prices have shot up to over USD 100/ ton, an increase of over 2x in the last year, rendering affected plants unviable. And domestic coal production capacity does not seem fully geared up yet to cater to 100% demand.

The deficit is expected to get worse in the next few months as we hit peak summer. And prognosis for the next few years does not look good. A simple extrapolation of demand-supply suggests that peak deficit could reach 30-40 GW levels in the next five years. Expected renewable power capacity addition of around 60 GW, almost all without any storage capacity in the same period, would exacerbate peak power deficit and price volatility.,/p>

There are already some calls for developing new thermal power projects to ease supply pressure. The government would do well to resist such pressure and examine alternate remedial measures like incentivising addition of storage capacity, demand side management and move to market based pricing of power. Meanwhile, soaring peak power prices should provide sufficient financial reasons to DISCOMs to overcome their financial concerns and commit to RTC renewable power. It is worth noting that SECI’s first peak power tender (1,200 MW solar-wind-storage hybrid capacity, peak power price of INR 6.12-6.85/ kWh) is still not fully contracted, more than 2 years after the auction date.


Recent reports

India Corporate Renewable Brief | Q4 2022   

This report provides a quarterly update on key trends and developments in the corporate renewable market including capacity addition, key players, pol...

Buy Report Download Executive Summary

India PV Module Intelligence Brief | Q4 2022   

This report captures quarterly trends in module demand and supply, import and domestic production volumes, supplier market shares, break-up by tech...

Buy Report

India Solar Compass | Q4 2022   

This report provides a detailed update of all key sector developments and trends in the quarter – capacity addition, leading players, tenders and po...

Buy Report Download Executive Summary

India Corporate Renewable Market   

India’s corporate renewable market is becoming more vibrant with strong demand, policy and technology levers. Driven by net zero targets and investo...

Buy Report Download Executive Summary

Green Hydrogen – Early Growth Opportunities   

Green hydrogen is a versatile fuel which may be used as an energy store, fuel and feedstock across multiple sectors. Refining and fertiliser industrie...

Buy Report Download Executive Summary

A business case for renewable energy certificates for Indian companies to meet RE 100 targets

C&I consumers account for 53% of power consumption but only 6% of this requirement is met from direct procurement of renewable power. In face of m...

Download
Award winnig research
We use cookies to offer you an optimal user experience and collect information on website usage.