Loading...

Andhra Pradesh decision a small victory for project developers


21 March 2022 | BRIDGE TO INDIA

Andhra Pradesh decision a small victory for project developers

Thirty two months after the Andhra Pradesh government’s flagrant attempt to renegotiate over 7,500 MW of renewable power PPAs, the state High Court has finally restored status quo. The High Court has, in an order dated 15 March 2022, directed the DISCOMs to honour contracted tariffs and clear all outstanding dues within six weeks. It has also definitively ruled that once projects have been duly allocated under a transparent process, tariffs may not be unilaterally revised by the state government, DISCOMs or even the state regulator. It has further directed the DISCOMs to not curtail power from renewable producers unless there is a risk to the grid.

Background
In July 2019, the then newly formed government in the state had sought to: i) reduce tariffs of all renewable projects; ii) cancel ‘must run’ status of renewable projects; and iii) cancel all renewable power procurement initiatives in pipeline. Subsequently, the High Court issued an order in September 2019 asking the DISCOMs to pay an interim tariff of INR 2.43/ kWh and 2.44/ kWh to solar and wind power producers respectively as against average contracted tariff of INR 4.30/ kWh.

Affected project developers
The impasse has been a major strain on finances of developers to the tune of INR 72 billion (USD 948 million) in aggregate pushing smaller developers to the brink of default. Total project portfolio, selling power to DISCOMs in Andhra Pradesh is estimated at 7,569 MW (split between solar – 3,907 MW and wind – 3,662 MW). Greenko (1,616 MW operational capacity), ReNew (777 MW), Adani (604 MW), Mytrah (364 MW) and Tata (305 MW) are the worst affected private developers.

Figure: Leading project developers in Andhra Pradesh, MW

Source: BRIDGE TO INDIA research
Note: Capacity excludes open access projects.

Implications for the sector
The High Court decision is being widely reported as a “significant positive” for investment sentiment in the sector. However, as we maintained in 2019, there was no justifiable basis for the state to renegotiate tariffs and it was only a matter of time before legal sanctity of contracts was held. The exercise was a mere political gimmick and an outrageous attempt to buy some respite for the financially struggling DISCOMs (rated B and C respectively by the Ministry of Power).

On the contrary, the fact that it took the High Court nearly 2.5 years to resolve such a black-and-white case is a blemish on the Indian legal system. Moreover, there remains considerable uncertainty for the affected developers. The DISCOMs will have to find an estimated INR 72 billion (USD 935 million) for past compensation and INR 27 billion (USD 350 million) for annual incremental payments to power producers. Being unable to clear all dues to power producers within six weeks as directed by the High Court, they may seek more time from the High Court or drag the process by appealing to the Supreme Court.

It is not even certain that other states would learn from the Andhra Pradesh precedent. After all, Andhra Pradesh chose to renegotiate PPAs despite failure of all such precedents. In the long run, the permanent cure lies in restoring financial health of DISCOMs by improving their governance and granting them operational autonomy. However, so long as state governments see an opportunity to curry favour with the masses by offering them cheaper power, they will keep meddling in the sector.  


Recent reports

Corporate renewable market -alternative procurement options

Corporate renewable market -alternative procurement options

Corporate consumers seeking to increase share of renewable power in their consumption mix have the option of using multiple short-term procurement routes like green power exchange, renewable energy certificates (RECs), I-RECs and green tariffs.

India Solar Rooftop Map | December 2023

India Solar Rooftop Map | December 2023

India Solar Rooftop Map is an info-graphic report providing a snapshot of rooftop solar market in India – capacity addition across states and consumer segments, market share of leading players and other key trends. Total rooftop solar capacity is estimated to have reached 14,484 MW by end of 2023. Total new installations in 2023 are estimated at 2,856 MW, up only 8% over previous year.

India Solar Map | December 2023

India Solar Map | December 2023

India Solar Map 2023 is an info-graphic report covering growth of utility scale solar sector – national and state-wise commissioned and pipeline capacity, leading market players and portfolio details of top 16 project developers. Capacity addition in 2023 fell 51% YOY to 5,924 MW taking total utility scale solar capacity to 59,840 MW. Total project pipeline stands at a record 74,161 MW.

India Corporate Renewable Brief | Q4 2023

India Corporate Renewable Brief | Q4 2023

This report provides an update on key trends and developments in the corporate renewable market including capacity addition, key players, policy & regulatory issuance, financing, PPA tariffs and other market trends.

India PV Module Intelligence Brief | Q4 2023

India PV Module Intelligence Brief | Q4 2023

This report captures quarterly trends in module demand and supply, import and domestic production volumes, supplier market shares, break-up by technology and rating, global market scenario, pricing trends across the value chain, key policy developments and market outlook.

India Solar Compass | Q4 2023

India Solar Compass | Q4 2023

This report provides a detailed update of all key sector developments and trends in the quarter – capacity addition, leading players, tenders and policy announcements, equipment prices, financial deals and other market developments. It also provides market outlook for the next two quarters.

To top