Total corporate renewable power capacity increased by 1,394 MW in Q1 2022 to reach 21,977 MW by 31 March 2022. Capacity addition in the quarter was split 67:4:29 amongst OA solar, wind and rooftop solar, with total capacity estimated to have reached 6,751 MW, 7,759 MW and 7,467 MW respectively.

Figure: Total installed C&I renewable capacity by 31 March 2022, MW

Source: BRIDGE TO INDIA research

Installation activity gathered pace 134% QOQ due to commissioning of projects delayed by Covid and implementation of BCD from April 2022.

The report provides a quarterly update on key trends and developments in the C&I renewable market including capacity addition, key players, government policy, tariff trends, financing and equipment prices.


Recent reports

India Corporate Renewable Brief | Q4 2023

India Corporate Renewable Brief | Q4 2023

This report provides an update on key trends and developments in the corporate renewable market including capacity addition, key players, policy & regulatory issuance, financing, PPA tariffs and other market trends.

India PV Module Intelligence Brief | Q4 2023

India PV Module Intelligence Brief | Q4 2023

This report captures quarterly trends in module demand and supply, import and domestic production volumes, supplier market shares, break-up by technology and rating, global market scenario, pricing trends across the value chain, key policy developments and market outlook.

India Solar Compass | Q4 2023

India Solar Compass | Q4 2023

This report provides a detailed update of all key sector developments and trends in the quarter – capacity addition, leading players, tenders and policy announcements, equipment prices, financial deals and other market developments. It also provides market outlook for the next two quarters.

Inter-state OA — opportunities and challenges

Inter-state OA — opportunities and challenges

Inter-state transmission system (ISTS) open access (OA) renewable market is growing strongly on the back of multiple drivers including a waiver from ISTS charges together with decarbonisation pressure on corporates and streamlined transmission connectivity approval process. However, the ISTS route savings are viable only for projects commissioned by June 2026 (at least 75% ISTS charge waiver).

India Corporate Renewable Brief | Q3 2023

India Corporate Renewable Brief | Q3 2023

This report provides an update on key trends and developments in the corporate renewable market including capacity addition, key players, policy & regulatory issuance, financing, PPA tariffs and other market trends.

India PV Module Intelligence Brief | Q3 2023

India PV Module Intelligence Brief | Q3 2023

This report captures quarterly trends in module demand and supply, import and domestic production volumes, supplier market shares, break-up by technology and rating, global market scenario, pricing trends across the value chain, key policy developments and market outlook.

To top