DGTR announces final safeguard duty recommendation

18 July 2018 |

The Directorate General of Trade Remedies (DGTR), Ministry of Commerce and Industry, has issued its final decision on the safeguard duty petition by domestic cell and module manufacturers. It has recommended a safeguard duty on imports of all cells and modules, irrespective of technology, for a period of two years – 25% in the first year falling to 20% and 15% in the subsequent six month periods respectively. The duty shall be applicable to imports from China, Malaysia and all developed countries. Imports from other developing countries have been exempted as they individually account for less than 3% of total imports into the country.

  •  If the recommendation is accepted, it will have no meaningful sustainable impact on domestic manufacturing because of the short duty period and no relief for SEZ (special economic zone) units;
  • The duty would pose financial and execution challenges for all ongoing projects and adversely impact government plans for the sector;
  • The industry should brace for an extended period of uncertainty as the duty saga is likely to linger on for the foreseeable future;

The decision is largely in line with expectations although the two-year application period is surprisingly short. It is not sufficient to encourage any new investments and nor does it allow existing manufacturers to upgrade their facilities and make any meaningful recovery. The other key aspect of the decision is that there is no relief provided to SEZ-based units including Mundra, Vikram and Waaree. These ‘domestic manufacturers’ would be subject to duty when they sell modules in the domestic market unless they are given a special dispensation by the government. But the domestic manufacturing industry excluding SEZ-based players can barely meet 5% of total domestic demand. That raises the question: why impose duties for benefit of some small manufacturers and risk growth in such a crucial sector?

We continue to maintain that the safeguard duty would be very damaging to the industry as well as to the government’s ambitious plans. Notwithstanding recent falls in module prices, most projects under execution would face viability challenges (capex increase of up to 15%, extra tariff requirement of INR 0.40/ kWh) and execution delays. MNRE has been promising protection from duty for projects where auctions have already been completed but there is no clarity available on that. Even where PPAs allow legal recourse through ‘change in law’ mechanism, there are bound to be drawn out disputes between the procurement agencies, DISCOMs and project developers.

We also believe that the arguments used to justify duty imposition are highly flawed. If the government accepts the recommendation to impose duty, there is a high chance of a successful appeal by other countries against the decision.

Some industry players have expressed relief that the DGTR decision, even if detrimental to developers and other downstream players, at least provides some clarity on way forward. Unfortunately, we disagree. For one, the final decision is still subject to ratification by the Board of Safeguard and Ministry of Finance. It is also possible that some developer(s) will find a spurious reason to hold up the process through legal appeal as happened last time. Moreover, we understand that domestic manufacturers are considering another petition for anti-dumping duty. The industry should brace for an extended period of uncertainty on this front.

Back
"; ?>

Recent reports

India Solar Rooftop Market Analytics   

This report presents trends and observations from over 16,000 rooftop solar installations with an aggregate capacity of 2,265 MW in our database. It p...

Buy Report Download Executive Summary

Forecasting and Scheduling Regulations   

India’s central electricity regulator, the Central Electricity Regulatory Commission (CERC), issued an amendment to the Deviation Settlement Mechani...

Buy Report Download Executive Summary

India RE Map | September 2019

India added 9,327 MW of utility scale wind and solar capacity in the last 12 months. Total installed RE capacity is estimated at 66,650 MW as on 30 Se...

Download

India Solar Compass Q2 2019   

Q2 was again a slow quarter for the solar sector with new capacity addition coming in at only 1,104 MW, down 55% over previous quarter and 28% below o...

Buy Report Download Executive Summary

India Solar Map | June 2019

Indian utility scale solar capacity reached 26,154 MW as on 31 March 2019. Capacity addition fell to 4,810 MW in FY 2019, down a steep 47% over previo...

Download

India Solar Rooftop Map | June 2019

India is estimated to have added a record 1,836 MW of rooftop solar capacity in FY 2019. Rooftop solar continues to grow rapidly registering a growth ...

Download
Award winnig research
We use cookies to offer you an optimal user experience and collect information on website usage.