Andhra Pradesh recently became the latest state to notify forecasting, scheduling and deviation settlement regulations for solar and wind power generation. It joins Karnataka, Chhattisgarh, Jharkhand and Uttarakhand, who have already announced these regulations. Six other states including Rajasthan, Gujarat, Madhya Pradesh, Tamil Nadu, Odisha and Manipur have announced draft regulations. Together, these states account for about 70% of operational and under development solar capacity. The primary objective of the new regulations is to make generators more accountable through enhanced forecasting requirements and penalizing them for deviation. Once operational, this should help facilitate large scale grid integration of intermittent renewable power while maintaining grid stability.

  • Industry experts believe that compliance cost for a single project, including penalties, may be around INR 0.02/kWh;
  • Generators can comply with the regulations on an individual basis or on a ‘virtual pool’ basis by joining others;
  • The regulations are highly desirable and developers would happily bear additional compliance cost in return for reduced curtailment risk;

The national power regulator, Central Electricity Regulatory Commission (CERC), first announced a regulation for deviation settlement mechanism back in 2014 and has made three subsequent amendments. All state regulations essentially follow the CERC regulation with some minor variations. For example, CERC regulations apply to wind farms with capacity greater than 10 MW and solar projects with capacity greater than 5 MW but Tamil Nadu and Andhra Pradesh regulations state applicability to all wind and solar generators selling power within the state. Similarly, penalties and permissible deviation limits vary marginally from state to state.

Under the new Andhra Pradesh regulations, power generators are required to provide State Load Dispatch Centre (SLDC) with day ahead and week ahead schedule in 15-minute time blocks with effect from 1 January 2018. They can revise their schedule once every ninety minutes – maximum 16 times a day for wind and 9 times a day for solar power. Penalties are proposed for deviations exceeding 15%. For deviations above 15%, penalties can be as high as INR 0.50-1.50/kWh.

Forecasting and scheduling regulations are commonplace in most of the western countries. As a result, there is abundant and growing expertise in technical and statistical modelling techniques, which can be replicated in India. Compliance will entail investment in new systems, upgradation of IT infrastructure and potential cost of penalties. Industry experts believe that the compliance cost for a single project, including penalties, may be around INR 0.02/kWh.

Generators can also come together to form ‘virtual pools’ to minimise group level deviations and reduce penalty cost risk. New plants expected to be commissioned after 1 January 2018 will not be allowed to commence commercial operation without the required forecasting mechanism in place.

The regulations may be seen as a new operational and financial burden for the sector but are an acknowledgement of its growing importance. Developers would be happy to bear this compliance cost than face greater risk of curtailment. We believe that these regulations are highly desirable as better forecasting and scheduling will enable integration of growing renewable capacity and pave way for future growth.


Recent reports

Corporate renewable market -alternative procurement options

Corporate renewable market -alternative procurement options

Corporate consumers seeking to increase share of renewable power in their consumption mix have the option of using multiple short-term procurement routes like green power exchange, renewable energy certificates (RECs), I-RECs and green tariffs.

India Solar Rooftop Map | December 2023

India Solar Rooftop Map | December 2023

India Solar Rooftop Map is an info-graphic report providing a snapshot of rooftop solar market in India – capacity addition across states and consumer segments, market share of leading players and other key trends. Total rooftop solar capacity is estimated to have reached 14,484 MW by end of 2023. Total new installations in 2023 are estimated at 2,856 MW, up only 8% over previous year.

India Solar Map | December 2023

India Solar Map | December 2023

India Solar Map 2023 is an info-graphic report covering growth of utility scale solar sector – national and state-wise commissioned and pipeline capacity, leading market players and portfolio details of top 16 project developers. Capacity addition in 2023 fell 51% YOY to 5,924 MW taking total utility scale solar capacity to 59,840 MW. Total project pipeline stands at a record 74,161 MW.

India Corporate Renewable Brief | Q4 2023

India Corporate Renewable Brief | Q4 2023

This report provides an update on key trends and developments in the corporate renewable market including capacity addition, key players, policy & regulatory issuance, financing, PPA tariffs and other market trends.

India PV Module Intelligence Brief | Q4 2023

India PV Module Intelligence Brief | Q4 2023

This report captures quarterly trends in module demand and supply, import and domestic production volumes, supplier market shares, break-up by technology and rating, global market scenario, pricing trends across the value chain, key policy developments and market outlook.

India Solar Compass | Q4 2023

India Solar Compass | Q4 2023

This report provides a detailed update of all key sector developments and trends in the quarter – capacity addition, leading players, tenders and policy announcements, equipment prices, financial deals and other market developments. It also provides market outlook for the next two quarters.

To top