MNRE announces a dizzying plan for the sector


27 November 2017 | BRIDGE TO INDIA

MNRE announces a dizzying plan for the sector

The Ministry of New and Renewable Energy (MNRE) has announced a new RE rollout plan entailing 91 GW of new solar and wind project tenders by March 2020. It is an ambitious attempt by the new MNRE administration to address private sector concerns about slowing project pipeline and lack of a clear roadmap. It envisages 67 GW of new solar project tenders and 24 GW of new wind project tenders by March 2020 as well as 20 GW of integrated solar module manufacturing capacity addition. With these planned projects, the new Minister for power and new and renewable energy, R.K. Singh, believes that India would “…comfortably achieve a rather conservative RE target of 175 GW by 2022 and even exceed it….”

The new plan provides new annual targets – 17 GW of solar projects are expected to be tendered out by March 2018, another 30 GW in the next 12 months and a further 30 GW in the subsequent 12 months. Similarly, 4 GW of wind projects are expected to be tendered out by March 2018, another 10 GW in the next 12 months and a further 10 GW in the subsequent 12 months. In total, it equates to issuing new tenders of 3.5 GW capacity every month – in contrast to an average of less than 0.6 GW every month in the last year. The plan includes development of up to 10 GW of capacity to come from floating solar power projects, offshore wind and hybrid solar-wind power systems.

The Minister has also separately laid out broad contours of a new domestic manufacturing policy– 30% capital subsidy is proposed to be allocated to integrated manufacturers (from polysilicon extraction to module manufacturing) on the basis of auctions. The winning bidders shall also be given priority in specific project development tenders.

Quite how the new plan makes sense in the current political and financial set up with weak power demand growth and stretched DISCOM finances is not clear to us. It seems more like a simple mathematical exercise rather than a well-considered, rigorously debated plan. We noted last week that the 175 GW target for 2022 is too ambitious in the context of India’s power needs and actual performance is lagging significantly behind targets compelling the government into making ever bolder announcements. The new plan has no detail on how it will address shortcomings of the earlier plan except the Minister stating that Renewable Purchase Obligations (RPOs) are mandatory and need to be adhered to strictly.

We find it hard to take the new plan seriously when it probably doesn’t even have support from other parts of the central government. The state governments and DISCOMs will also fiercely resist any encroachment on their decision-making authority. It lacks sufficient detail, is off-putting for all stakeholders and instead of providing comfort to the private sector, it unfortunately presents a picture of disarray and confusion.


Recent reports

Corporate renewable market -alternative procurement options

Corporate renewable market -alternative procurement options

Corporate consumers seeking to increase share of renewable power in their consumption mix have the option of using multiple short-term procurement routes like green power exchange, renewable energy certificates (RECs), I-RECs and green tariffs.

India Solar Rooftop Map | December 2023

India Solar Rooftop Map | December 2023

India Solar Rooftop Map is an info-graphic report providing a snapshot of rooftop solar market in India – capacity addition across states and consumer segments, market share of leading players and other key trends. Total rooftop solar capacity is estimated to have reached 14,484 MW by end of 2023. Total new installations in 2023 are estimated at 2,856 MW, up only 8% over previous year.

India Solar Map | December 2023

India Solar Map | December 2023

India Solar Map 2023 is an info-graphic report covering growth of utility scale solar sector – national and state-wise commissioned and pipeline capacity, leading market players and portfolio details of top 16 project developers. Capacity addition in 2023 fell 51% YOY to 5,924 MW taking total utility scale solar capacity to 59,840 MW. Total project pipeline stands at a record 74,161 MW.

India Corporate Renewable Brief | Q4 2023

India Corporate Renewable Brief | Q4 2023

This report provides an update on key trends and developments in the corporate renewable market including capacity addition, key players, policy & regulatory issuance, financing, PPA tariffs and other market trends.

India PV Module Intelligence Brief | Q4 2023

India PV Module Intelligence Brief | Q4 2023

This report captures quarterly trends in module demand and supply, import and domestic production volumes, supplier market shares, break-up by technology and rating, global market scenario, pricing trends across the value chain, key policy developments and market outlook.

India Solar Compass | Q4 2023

India Solar Compass | Q4 2023

This report provides a detailed update of all key sector developments and trends in the quarter – capacity addition, leading players, tenders and policy announcements, equipment prices, financial deals and other market developments. It also provides market outlook for the next two quarters.

To top