MNRE plays a dangerous game


06 August 2018 | BRIDGE TO INDIA

MNRE plays a dangerous game

SECI has cancelled 2,400 MW of the 3,000 MW solar tender for which an auction was completed about three weeks ago. Capacity was won by Acme (600 MW, INR 2.44/ kWh), Azure (300 MW, 2.64), Canadian Solar (200 MW, INR 2.70), Adani (300 MW, INR 2.71), ReNew (500 MW, INR 2.71) and SoftBank (1,100 MW, INR 2.71). All bids other than Acme’s have been rejected. This cancellation comes in the wake of other recent cancellations by Uttar Pradesh (1,000 MW state tender, winning tariffs of INR 3.48-3.55) and Gujarat (500 MW state tender, winning tariffs of INR 2.98-3.06). Meanwhile, SECI has also cancelled a 2,000 MW pan India wind tender, which was undersubscribed because of developer concerns around transmission capacity.

  • It is not logical for procurement authorities to cancel auctions when winning tariffs are well below the ceiling tariffs;
  • Unrelenting focus on price is detracting from the government plans and overall vision for RE sector;
  • Procurement authorities run the risk of turning developers away if tender cancellations are not curbed immediately;

The reason given for all the solar tender cancellations is that the winning tariffs were deemed to be too high by MNRE and/or the DISCOMs. But the winning tariffs in the SECI tender were well below the ceiling tariff of INR 2.93 (there was no ceiling tariff in other tenders). Ceiling tariffs are supposed to be approved by power purchasers in advance to ensure that winning tariffs are acceptable to them. Logically, therefore, the reason given for tender cancellation does not make sense. Additionally, it is clear that MNRE and SECI have been acting in haste to issue as many new tenders as possible without seeking due purchasing commitments from DISCOMs.

So far in 2018, auctions have been completed for 12,570 MW of solar projects. Almost one-third of this, 3,900 MW capacity, has been cancelled. The cancellations are obviously a setback to the government’s growth plans for RE. We believe that increasing tender cancellations is a damaging development for other reasons. It shows growing mismatch between expectations of procurement authorities and project developers and indicates a likely fractious relationship between the two over potentially troubling issues including safeguard duty, transmission infrastructure, grid curtailment etc. More importantly, if this trend persists, developers are bound to lose confidence in the sector. The lesson for MNRE and SECI is clear in our view. Rather than relentlessly issuing new tenders, they need to follow a more orderly project development process in close coordination with DISCOMs, Power Grid Corporation and other agencies to avoid such incidents.

Procurement authorities rightly require developers to provide bank guarantees and other documentary evidence to ensure their commitment. But developers also spend considerable time and effort in participating in tender processes. Shouldn’t they be compensated every time an authority backs out of a tender for no valid reason?


Recent reports

Corporate renewable market -alternative procurement options

Corporate renewable market -alternative procurement options

Corporate consumers seeking to increase share of renewable power in their consumption mix have the option of using multiple short-term procurement routes like green power exchange, renewable energy certificates (RECs), I-RECs and green tariffs.

India Solar Rooftop Map | December 2023

India Solar Rooftop Map | December 2023

India Solar Rooftop Map is an info-graphic report providing a snapshot of rooftop solar market in India – capacity addition across states and consumer segments, market share of leading players and other key trends. Total rooftop solar capacity is estimated to have reached 14,484 MW by end of 2023. Total new installations in 2023 are estimated at 2,856 MW, up only 8% over previous year.

India Solar Map | December 2023

India Solar Map | December 2023

India Solar Map 2023 is an info-graphic report covering growth of utility scale solar sector – national and state-wise commissioned and pipeline capacity, leading market players and portfolio details of top 16 project developers. Capacity addition in 2023 fell 51% YOY to 5,924 MW taking total utility scale solar capacity to 59,840 MW. Total project pipeline stands at a record 74,161 MW.

India Corporate Renewable Brief | Q4 2023

India Corporate Renewable Brief | Q4 2023

This report provides an update on key trends and developments in the corporate renewable market including capacity addition, key players, policy & regulatory issuance, financing, PPA tariffs and other market trends.

India PV Module Intelligence Brief | Q4 2023

India PV Module Intelligence Brief | Q4 2023

This report captures quarterly trends in module demand and supply, import and domestic production volumes, supplier market shares, break-up by technology and rating, global market scenario, pricing trends across the value chain, key policy developments and market outlook.

India Solar Compass | Q4 2023

India Solar Compass | Q4 2023

This report provides a detailed update of all key sector developments and trends in the quarter – capacity addition, leading players, tenders and policy announcements, equipment prices, financial deals and other market developments. It also provides market outlook for the next two quarters.

To top