Loading...

New RTC guidelines offer little hope for pure play renewable IPPs


20 November 2020 | BRIDGE TO INDIA

New RTC guidelines offer little hope for pure play renewable IPPs

The Ministry of Power has amended competitive bidding guidelines for procuring ‘round-the-clock’ (RTC) power by blending renewable power with power from other sources. Minimum share of renewable power remains at 51%. Main change pertains to relaxation in source of other power – bidders are free to procure non-renewable power from any source as against being restricted to only coal-fired power. There is also no longer any restriction for renewable and non-renewable plants to be in the same Regional Load Desptach Centre (RLDC) area. However, the bidders are required to specify only one non-renewable source together with share of non-renewable power as well as generating stations with uncontracted capacity upfront.

  • Despite relaxation in power sourcing, thermal power seems like the obvious choice for blending with renewable power;
  • Steep increase in penalties and requirement to match L1 tariff would be major source of irritation for developers;
  • DISCOMs would be better served by procuring renewable and non-renewable power separately on their own;

There is no change in the minimum CUF or availability requirement of 85% annually as well as for four peak hours every day (as specified by the respective RLDC). But penalty for not fulfilling these requirements or providing specified renewable power output every year has been increased steeply from 25% to 400% of applicable tariff for the respective shortfall.

Projects up to 1,000 MW are required to achieve financial closure and COD within 18 and 24 months respectively (24 and 30 months respectively for projects greater than 1,000 MW). Bidders will be required to submit a four-part tariff bid – tariff for renewable power, fixed charges and variable charges for fuel and transportation costs for non-renewable power. Surprisingly, there is no separate component for non-renewable O&M costs. Projects would be allocated on the basis of weighted average levellised tariff, computed as per CERC guidelines. Winning bidders are required to match L1 tariff, which would be a source of irritation for the developers.

Overall, the changes are largely positive for developers. Despite relaxation in source of non-renewable power, thermal power would be the obvious choice both for availability of spare capacity and cost competitive reasons. Unfortunately, the scheme remains beyond scope of pure play renewable IPPs. Renewable power alone with storage would not be able to compete with conventional power. And a tie-up with an external entity is implausible as no developer would be able to assume third party risk over 25 years. That leaves only a handful of IPPs straddling both renewable and thermal power sectors – mainly NTPC, Adani, JSW and Sembcorp – potentially interested in the scheme.

From a DISCOM perspective, getting round-the-clock power with specified share of peak power and renewable power is desirable. But we maintain that they would be better off in procuring renewable and non-renewable power separately on their own. It is not clear why they need developers to supply blended power through a highly restrictive tender process.

SECI has already issued a 5,000 MW RTC tender. Bid submission date has been repeatedly extended due to various changes sought by developers. Revised guidelines should allow the tender to finally go ahead. Another extension is expected for incorporation of revised guidelines. Small number of potential bidders means that the tender is unlikely to attract competitive bids.


Recent reports

India Solar Map | December 2023

India Solar Map | December 2023

India Solar Map 2023 is an info-graphic report covering growth of utility scale solar sector – national and state-wise commissioned and pipeline capacity, leading market players and portfolio details of top 16 project developers. Capacity addition in 2023 fell 51% YOY to 5,924 MW taking total utility scale solar capacity to 59,840 MW. Total project pipeline stands at a record 74,161 MW.

India Corporate Renewable Brief | Q4 2023

India Corporate Renewable Brief | Q4 2023

This report provides an update on key trends and developments in the corporate renewable market including capacity addition, key players, policy & regulatory issuance, financing, PPA tariffs and other market trends.

India PV Module Intelligence Brief | Q4 2023

India PV Module Intelligence Brief | Q4 2023

This report captures quarterly trends in module demand and supply, import and domestic production volumes, supplier market shares, break-up by technology and rating, global market scenario, pricing trends across the value chain, key policy developments and market outlook.

India Solar Compass | Q4 2023

India Solar Compass | Q4 2023

This report provides a detailed update of all key sector developments and trends in the quarter – capacity addition, leading players, tenders and policy announcements, equipment prices, financial deals and other market developments. It also provides market outlook for the next two quarters.

Inter-state OA — opportunities and challenges

Inter-state OA — opportunities and challenges

Inter-state transmission system (ISTS) open access (OA) renewable market is growing strongly on the back of multiple drivers including a waiver from ISTS charges together with decarbonisation pressure on corporates and streamlined transmission connectivity approval process. However, the ISTS route savings are viable only for projects commissioned by June 2026 (at least 75% ISTS charge waiver).

India Corporate Renewable Brief | Q3 2023

India Corporate Renewable Brief | Q3 2023

This report provides an update on key trends and developments in the corporate renewable market including capacity addition, key players, policy & regulatory issuance, financing, PPA tariffs and other market trends.

To top