Forecasting and Scheduling Regulations


India’s central electricity regulator, the Central Electricity Regulatory Commission (CERC), issued an amendment to the Deviation Settlement Mechanism (DSM) regulations in 2015 to apply them to solar and wind power. The regulations aim to ensure grid stability in view of the increasing capacity of variable renewable power. All inter-state grid connected solar and wind power plants are mandated to forecast their generation schedule for day-ahead and week-ahead periods.

Note: Fixed rate is the weighted average of PPAs of all power plants connected to the respective pooling station.

Many states have subsequently issued individual regulations on forecasting, scheduling and deviation settlement broadly in line with the CERC framework. This report compares policy framework across states and assesses challenges faced by project developers in implementation. It also includes a high level overview of similar framework in other countries.


Recent reports

India Solar Compass Q3 2020   

India added just 351 MW of solar power generation capacity in Q2 2020 taking total installed capacity to 38,377 MW by 30 June 2020....

Buy Report Download Executive Summary

Solar Manufacturing Prospects   

Buoyed by government promises of customs duty on imports and financial incentives, solar manufacturing sector is witnessing renewed interest....

Buy Report Download Executive Summary

India Solar Rooftop Map | June 2020

India’s operational rooftop solar capacity reached 5,953 MW as on 30 June 2020. Only 1,140 MW capacity is estimated to have been added in the twelve...

Download

India Renewable Map | June 2020

India’s utility scale solar and wind capacity reached 69,808 MW as on 30 June 2020. Only 6,284 MW of new capacity was added over last 12 months, dow...

Download

India Solar Compass Q2 2020   

India added just 351 MW of solar power generation capacity in Q2 2020 taking total installed capacity to 38,377 MW by 30 June 2020....

Buy Report Download Executive Summary

Transmission planning, implementation and status   

Transmission remains a critical bottleneck to growth of India’s renewable power sector....

Buy Report Download Executive Summary
We use cookies to offer you an optimal user experience and collect information on website usage.