Loading...

Solar PV tariffs in Tamil Nadu fall to INR 5.97/kWh, but INR 6.8/kWh is more viable


31 January 2013 | Jasmeet Khurana

Solar PV tariffs in Tamil Nadu fall to INR 5.97/kWh, but INR 6.8/kWh is more viable

Tamil Nadu today opened the financial bids received for allocations under its state policy. The state had received a subdued response with bids totaling 499MW for a tender of 1,000MW (refer to our earlier blog post to read more). Initial reports suggest that financial bids have been opened for 493MW and the lowest bid has touched INR 5.97/kWh (for a 10MW project by Mohan Breweries).

  • The lowest bid has touched INR 5.97/kWh, the average bid is just over INR 8/kWh
  • The options for determination and negotiation of tariffs are still open.
  • Large parts of the state are reeling under severe power cuts and solar is the only source of power that can help the state meet its peak power needs in a short duration of time.

Tamil Nadu has thus seen the lowest tariffs in the country, primarily owing to the provision for a 5% annual escalation for 10 years in tariff. However, the average bid was just over INR 8 kWh and some prominent bidders such as Welspun (INR 8.56/kWh) and Lanco (INR 8.2/kWh) were significantly higher than the current norm in the country (around INR 7-7.5 kW/h).

BRIDGE TO INDIA had earlier estimated that the lowest tariff in Tamil Nadu could touch INR 6.2/kWh (refer). This tariff was based on very aggressive assumptions with an expected IRR of 12%. While some industry experts communicated to us that this estimate was unrealistically low, we were surprised to see that the lowest tariff is even lower than that. A more realistic tariff with a 5% escalation for the first 10 years that should be acceptable to developers, the state and the lenders is likely to be around INR 6.8/kWh.

The state had planned for a mechanism under which it would ask all bidders to meet the lowest bid (L1). However, due to the subdued interest and complications involved in negotiating such a price with the developers, first signs are emerging that the Tamil Nadu Power Generation and Distribution Corporation Ltd. (TANGEDCO) is willing to consider other options such as taking a median tariff for all projects. The options for determination and negotiation of tariffs are still open.

However, even if the final tariffs are acceptable to developers, we expected ongoing challenges. The revolving line of credit that promises to be a guarantee of payment to developers is unlikely to help them in raising non-recourse debt. One clause in the agreement implies that the government will have the right to make amendments in the policy and guidelines of the agreement from time to time. Such a clause places the developer in a position that is not protected from policy or governance changes. Another clause states that the Power Purchase Agreement is subject to approval from the Tamil Nadu Electricity Regulatory Commission. The time required to obtain such approval from the TNERC is not known and may create delays.

BRIDGE TO INDIA believes that if the PPA does not get TNERC’s approval in time, developers will face difficulties in achieving financial closure. This will further strain the already stringent eight-month commissioning deadline.

The state must, however, be commended on taking an initiative to promote solar power in spite of its financial problems. Large parts of the state are reeling under severe power cuts and solar is the only source of power that can help the state meet its peak power needs in a short duration of time. If Tamil Nadu is able to take all steps necessary to help the allocated capacity of 493MW to come up, it will still be a more than respectable target achievement.

Read our Tamil Nadu Solar Policy Brief for more.

Jasmeet Khurana works on project performance benchmarking, success factors for module sales, financing and bankability of projects in India.

What are your thoughts? Leave a comment below.


Recent reports

India PV Module Intelligence Brief | Q3 2024

India PV Module Intelligence Brief | Q3 2024

This report encapsulates quarterly trends in module demand and supply, import and domestic production volumes, supplier market share, break-up by technology and rating, global market scenario, pricing across the value chain, key policy developments and market outlook.

India Corporate Renewable Brief | Q3 2024

India Corporate Renewable Brief | Q3 2024

This report provides a quarterly update on key trends and developments in the corporate renewable market including capacity addition, key players, policy issuances, financing, equipment prices and other market trends.

India Renewable Compass | Q3 2024

India Renewable Compass | Q3 2024

This report provides a detailed update of all key sector developments and trends in the quarter – capacity addition, leading players, tenders and policy announcements, equipment prices, financial deals and other market developments. It also provides market outlook for the next two quarters.

India Solar Rooftop Map | June 2024

India Solar Rooftop Map | June 2024

India Solar Rooftop Map is an info-graphic report providing a snapshot of rooftop solar market in India – capacity addition across states and consumer segments, market share of leading players and other key trends. Total rooftop solar capacity is estimated to have reached 16,914 MW by June 2024. Total new installations in year-ending June 2024 are estimated at 4,151 MW, up a staggering 73% over previous year.

Powering up renewables with battery energy storage systems

Powering up renewables with battery energy storage systems

India’s battery energy storage systems (BESS) market is poised for significant expansion, driven by ambitious renewable energy (RE) targets and an increasing need for grid stability. Government initiatives and technological advancements are propelling this growth. However, supply chain risks and cost challenges remain.

India Renewable Map | June 2024

India Renewable Map | June 2024

This info-graphic report provides a complete overview of the renewable sector including solar and wind installed capacity, leading players and their market shares, tariff trends and other market trends. India’s total solar and wind capacity reached 117,085 MW by 30 June 2024. New capacity addition in the last 12 months was 14,238 MW, increased by 32% y-o-y.

To top