Loading...

Transmission outlook improving


16 August 2020 | BRIDGE TO INDIA

Transmission outlook improving

CERC, the national power sector regulator, has issued a set of proposed amendments to procedure for grant of inter-state transmission system (ISTS) connectivity approval to renewable projects. Among the major proposals is relaxation in the onerous bank guarantee requirements. Deadline for commissioning of transmission line and obligation for payment of transmission charges are proposed to be linked to scheduled COD of renewable projects rather than fixed dates. Timelines to achieve specific milestones after award of connectivity approval are also proposed to be relaxed along with a proposal to enable sharing of dedicated transmission lines between various developers.

  • Transmission has been a critical bottleneck to growth of the renewable sector;
  • Ministry of Power, MNRE and CERC have collectively taken several steps to address associated challenges;
  • These initiatives are highly encouraging for the renewable sector although some teething issues still remain;

Proposed changes in bank guarantee requirements include linking guarantee amount to type and status of bays allocated to the project instead of project capacity and complete waiver of construction bank guarantee if the developer constructs transmission bays at the ISTS substation. Moreover, CERC has proposed to reduce time of return of guarantees from six months to one month post renewable project COD.

These changes come on back of several other steps taken by Ministry of Power, MNRE and CERC over the last few years:

  1. The Central Transmission Utility (CTU), responsible for ISTS planning and network management, is being demerged from Power Grid Corporation to address conflict of interest between the latter’s role as transmission system developer and network manager.
  2. MNRE and SECI are now part of transmission planning committee resulting in better planning and synchronisation of transmission infrastructure development with renewable project development.
  • The Green Energy Corridor and Renewable Energy Zone schemes are designed to create evacuation infrastructure for new renewable power capacity of 106.5 GW by 2022. Total estimated cost of these schemes is INR 647 billion (USD 8.6 billion) is being funded by the government together with concessional finance from development FIs.
  1. More transmission work is being tendered out through competitive bidding, as against allocated directly to Power Grid Corporation under cost plus mechanism, reducing cost and time required for new infrastructure by up to 30-50%.
  2. MNRE recently extended commissioning deadline for projects eligible for ISTS charge waiver from December 2022 to June 2023 besides providing blanket waiver to projects implemented under the PSU scheme and manufacturing-linked tender.

Figure: Renewable Energy Zone scheme target, GW

Source: CERC, BRIDGE TO INDIA research

Overall, these initiatives are highly encouraging for the renewable sector. Transmission has been a critical bottleneck to growth of the sector. Poor coordination, planning and execution have led to extensive delays and even cancellation of renewable power projects.

For sure, there are still many teething issues for renewable projects. Critically, there is no guarantee by the CTU that transmission infrastructure would be available by scheduled COD of the renewable project. And there is no provision for compensation in case or transmission infrastructure is not ready. There is also even now uncertainty in getting connectivity approvals particularly in Rajasthan. Heavy regional concentration of capacity – more than 50% of total solar pipeline of 41 GW is proposed to be located in Rajasthan – is still creating bottlenecks.


Recent reports

India Solar Map | December 2023

India Solar Map | December 2023

India Solar Map 2023 is an info-graphic report covering growth of utility scale solar sector – national and state-wise commissioned and pipeline capacity, leading market players and portfolio details of top 16 project developers. Capacity addition in 2023 fell 51% YOY to 5,924 MW taking total utility scale solar capacity to 59,840 MW. Total project pipeline stands at a record 74,161 MW.

India Corporate Renewable Brief | Q4 2023

India Corporate Renewable Brief | Q4 2023

This report provides an update on key trends and developments in the corporate renewable market including capacity addition, key players, policy & regulatory issuance, financing, PPA tariffs and other market trends.

India PV Module Intelligence Brief | Q4 2023

India PV Module Intelligence Brief | Q4 2023

This report captures quarterly trends in module demand and supply, import and domestic production volumes, supplier market shares, break-up by technology and rating, global market scenario, pricing trends across the value chain, key policy developments and market outlook.

India Solar Compass | Q4 2023

India Solar Compass | Q4 2023

This report provides a detailed update of all key sector developments and trends in the quarter – capacity addition, leading players, tenders and policy announcements, equipment prices, financial deals and other market developments. It also provides market outlook for the next two quarters.

Inter-state OA — opportunities and challenges

Inter-state OA — opportunities and challenges

Inter-state transmission system (ISTS) open access (OA) renewable market is growing strongly on the back of multiple drivers including a waiver from ISTS charges together with decarbonisation pressure on corporates and streamlined transmission connectivity approval process. However, the ISTS route savings are viable only for projects commissioned by June 2026 (at least 75% ISTS charge waiver).

India Corporate Renewable Brief | Q3 2023

India Corporate Renewable Brief | Q3 2023

This report provides an update on key trends and developments in the corporate renewable market including capacity addition, key players, policy & regulatory issuance, financing, PPA tariffs and other market trends.

To top