Bidding frenzy continues in the renewable sector

Bidding frenzy continues in the renewable sector


29 December 2017 | Mudit Jain

Bidding frenzy continues in the renewable sector

Three major auctions were completed last week – two for solar projects by SECI (Bhadla solar park 500 MW and 250 MW respectively) and one for wind projects by Gujarat Urja Vikas Nigam (GUVNL, fully owned by Gujarat government) (500 MW). The solar projects were won by Hero Future (300 MW), Softbank (200 MW), Azure (200 MW) and ReNew (50 MW) at tariffs between INR 2.47-2.49/ kWh (USD 0.04), a very slight increase over the previous auction tariff in Bhadla solar park back in May 2017. Wind tariffs, on the other hand, fell even further to INR 2.43-2.45/ kWh. Projects were won by Sprng (owned by Actis, 197 MW), KP (30 MW), Verdant (100 MW), Engie (30 MW), Powerica (50 MW) and ReNew (93 MW).

Figure: Recent bid tariffs for solar and wind tenders

Note: NTPC 250 MW DCR (domestic content requirement) auction in October 2017 is not shown as it has unique pricing fundamentals.

In the previous Bhadla auctions in May 2017, tariffs had touched an all-time low of INR 2.44/ kWh. Since then, module prices have risen by around 20% to USD 0.36/W. Including other cost inflationary factors such as 7.5% import duty on modules and 5% GST, capex has increased cumulatively by about 20% in the last six months. It is remarkable that tariffs have remained relatively unchanged despite such significant increase in capex and a very real risk of anti-dumping/ safeguard duties on modules. There is no material change in any other factors including solar park charges or financing costs in this period.

As per our analysis, module prices would need to fall to an impossible USD 0.16/W (55% reduction in 10 months) for winning bidders to earn a project IRR of 11%. This ignores the impending risk of anti-dumping duties.

The fall in wind tariffs, 33% in just ten months is equally stunning and hard to explain. There is no underlying industry trend that justifies such a significant tariff reduction.

The only way to explain the latest tariffs is that the developers, concerned by slowdown in power procurement, are anxious to win capacity at any cost. We have maintained for some time that renewable auction tariffs are becoming unsustainable, but the problem is getting even worse. Clearly, the industry is not convinced by the MNRE’s new exuberant plan of auctioning 17 GW of solar and 3-4 GW of wind projects by March 2018. But not only are the developers taking undue risk in these auctions, there is also a growing hazard that as and when there is a tariff correction, the DISCOMs would walk away creating challenges for projects yet to come.


Recent reports

India Solar Map | December 2024

India Solar Map | December 2024

India Solar Map 2024 is an info-graphic report covering growth of ground-mounted solar sector – national and state wise solar installation growth, ground-mounted solar EPC cost, player wise breakup of ALMM capacity, portfolio details of top 10 developers and trend of solar allocations. As of December, total ground-mounted solar installations reached 80,879 MW, reflecting a 20% CAGR since...

India PV Module Intelligence Brief | Q4 2024

India PV Module Intelligence Brief | Q4 2024

This report encapsulates quarterly trends in module demand and supply, import and domestic production volumes, supplier market share, break-up by technology and rating, global market scenario, pricing across the value chain, key policy developments and market outlook.

India Corporate Renewable Brief | Q4 2024

India Corporate Renewable Brief | Q4 2024

This report provides a quarterly update on key trends and developments in the corporate renewable market including capacity addition, key players, policy issuances, financing, equipment prices and other market trends.

India Renewable Compass | Q4 2024

India Renewable Compass | Q4 2024

This report provides a detailed update of all key sector developments and trends in the quarter – capacity addition, leading players, tenders and policy announcements, equipment prices, financial deals and other market developments. It also provides market outlook for the next two quarters. 

India PV Module Intelligence Brief | Q3 2024

India PV Module Intelligence Brief | Q3 2024

This report encapsulates quarterly trends in module demand and supply, import and domestic production volumes, supplier market share, break-up by technology and rating, global market scenario, pricing across the value chain, key policy developments and market outlook.

India Corporate Renewable Brief | Q3 2024

India Corporate Renewable Brief | Q3 2024

This report provides a quarterly update on key trends and developments in the corporate renewable market including capacity addition, key players, policy issuances, financing, equipment prices and other market trends.

To top