Loading...

India’s uniquely complex bidding quagmire


16 July 2019 | BRIDGE TO INDIA

India’s uniquely complex bidding quagmire

Gujarat has asked winning bidders in its May 2019 wind auction for 1,000 MW projects to match the lowest tariff of INR 2.80/ kWh bid by Enerfra, a local developer. Seven other winners including Adani, ReNew, Greenko, EdF, Vena, INOX and Powerica, who had bid tariffs between INR 2.81-2.95/ kWh have been told that PPAs will be not signed unless developers reduce tariff to INR 2.80/ kWh. Meanwhile, Acme, India’s largest solar developer, is seeking to cancel its 600 MW winning bid of INR 2.59/ kWh in a 2,000 MW solar auction completed by NTPC in August 2018. The company’s argument is that its project has not been approved by the Telangana state regulator in the stipulated timeframe of 2 months – a condition precedent in the PPA – allowing it to terminate the PPA.

  • DISCOMs are reluctant buyers of RE as it is ill suited to meet their peak load requirements and balancing costs are estimated to be high;
  • In a highly competitive market, the developers continue to bid aggressively in response;
  • Both sides are fixated on prices leading to jitters and increasing risk of bid cancellations, tariff renegotiation, curtailment and poor execution;

Both instances reflect a growing malaise in the RE sector. Gujarat’s rationale for renegotiation is that the tariff premium of INR 0.15/ kWh (+5.4%) in the winning bids is too high. That doesn’t make sense and also goes against the auction rules. The real reason of course is that the DISCOMs are stuck between a rock and a hard place. Deeply stressed financial position and political pressure to keep tariffs low is forcing them to squeeze RE developers instead. Despite wind and solar power being far cheaper than all other sources of power, they are reluctant buyers as RE is ill suited to meet their peak load requirements. They still need to procure more expensive conventional power with high fixed costs. RE also has higher transmission costs and its variable output profile/ ‘must run’ status poses all sorts of challenges to the grid. In a study completed in 2017, the Central Electricity Authority (CEA) estimated additional cost of balancing RE at around INR 1.50/ kWh. Gujarat has already cancelled two solar tenders aggregating 1,200 MW capacity because the tariffs were “too high” and it might do so again.

Unfortunately, the developers have been only too keen to comply. Bidding has stayed aggressive consistently with developers taking a favourable view of the operating and financial environment. Our calculations show that with execution challenges mounting and the financing environment also getting tough, most ISTS solar and wind bids below INR 2.70 and INR 2.90 respectively are not viable. Risk-adjusted equity returns are barely in double digits.

The implications for all stakeholders are unsavoury. It remains to be seen how developers would sustain their aggressive bids. IPO plans are looking unrealistic and the secondary market is also challenging. The risk of bid cancellations, tariff renegotiation, curtailment and delayed project execution is high and rising. Relationships between generators and offtakers are getting fraught and do not bode well for future of the sector.


Recent reports

Corporate renewable market -alternative procurement options

Corporate renewable market -alternative procurement options

Corporate consumers seeking to increase share of renewable power in their consumption mix have the option of using multiple short-term procurement routes like green power exchange, renewable energy certificates (RECs), I-RECs and green tariffs.

India Solar Rooftop Map | December 2023

India Solar Rooftop Map | December 2023

India Solar Rooftop Map is an info-graphic report providing a snapshot of rooftop solar market in India – capacity addition across states and consumer segments, market share of leading players and other key trends. Total rooftop solar capacity is estimated to have reached 14,484 MW by end of 2023. Total new installations in 2023 are estimated at 2,856 MW, up only 8% over previous year.

India Solar Map | December 2023

India Solar Map | December 2023

India Solar Map 2023 is an info-graphic report covering growth of utility scale solar sector – national and state-wise commissioned and pipeline capacity, leading market players and portfolio details of top 16 project developers. Capacity addition in 2023 fell 51% YOY to 5,924 MW taking total utility scale solar capacity to 59,840 MW. Total project pipeline stands at a record 74,161 MW.

India Corporate Renewable Brief | Q4 2023

India Corporate Renewable Brief | Q4 2023

This report provides an update on key trends and developments in the corporate renewable market including capacity addition, key players, policy & regulatory issuance, financing, PPA tariffs and other market trends.

India PV Module Intelligence Brief | Q4 2023

India PV Module Intelligence Brief | Q4 2023

This report captures quarterly trends in module demand and supply, import and domestic production volumes, supplier market shares, break-up by technology and rating, global market scenario, pricing trends across the value chain, key policy developments and market outlook.

India Solar Compass | Q4 2023

India Solar Compass | Q4 2023

This report provides a detailed update of all key sector developments and trends in the quarter – capacity addition, leading players, tenders and policy announcements, equipment prices, financial deals and other market developments. It also provides market outlook for the next two quarters.

To top