Loading...

Time for an overhaul of the tender framework


07 February 2021 | BRIDGE TO INDIA

Time for an overhaul of the tender framework

Gujarat has done it again. The state’s power procurement agency, Gujarat Urja Vikas Nigam Limited (GUVNL), has cancelled projects awarded under its 700 MW Dholera and 100 MW Raghanesda solar park tenders. Auctions for the two tenders were completed in August 2020 and September 2020 respectively with projects being awarded to Tata Power, Vena, ReNew, O2 Power and SJVN at tariffs between INR 2.73-2.81/ kWh. GUVNL had already issued LOAs (letters of award) to the successful bidders but has now reversed its decision in view of low tariffs discovered in recent auctions.

  • Cancellation of bids would lead to substantial losses for the successful developers, who had started making concrete progress on project development;
  • GUVNL’s decision is inexplicable since both tenders were repeatedly undersubscribed due to challenging locations with high flooding and corrosion risk;
  • An urgent overhaul of tender framework is required to make the process sacrosanct and reduce opportunistic leeway for all parties;

GUVNL believes that since tariffs have been coming down, it should conduct fresh auctions and seek lower tariffs to protect consumer interests. It had previously cancelled a 500 MW solar auction completed in April 2018 (tariffs of INR 2.98-3.06/ kWh) and another 700 MW solar auction completed in December 2018 (INR 2.34-2.89/ kWh) for the same reasons.

GUVNL’s decision would lead to substantial losses for the successful developers. Mindful of the short construction period (15 months) and tough site conditions, they had already paid solar park charges and were making concrete progress on project development. Some of them have even placed equipment orders. For its part, GUVNL had also filed petitions with the state regulator for approval of auction tariffs and was apparently in regular touch with the developers for ensuring speedy execution.

Moreover, GUVNL is well aware that Dholera and Raghanesda are challenging locations for solar projects. The sites, located close to the coast, have silty soil and face extremely high flooding and corrosion risk. Projects require special design entailing higher capital (about INR 3-4 million/ MW, capital cost uplift of about 6%) and operating costs to deal with these risks. The two tenders were repeatedly undersubscribed until GUVNL increased ceiling tariff to INR 2.92.

We believe that cancellation of tenders with benefit of hindsight is indefensible. Unfortunately, the developers have no legal protection under the existing bidding framework until the PPAs are signed and approved by respective regulators. Unwillingness of DISCOMs to sign PPAs and arbitrary cancellation of tenders are draining market confidence.

An urgent overhaul of the tender framework is required to make auctions sacrosanct and reduce opportunistic leeway for all parties. Amongst other measures, tenders should be issued only after identifying offtakers and with ceiling tariffs, pre-approved by the regulators. Second, the tenders should have clearly specified deadlines for PPA execution and project construction. Thirdly, if the procurement agencies decide unilaterally to not proceed with a tender after completing auction, they should compensate successful bidders for their bidding effort and cost.


Recent reports

Corporate renewable market -alternative procurement options

Corporate renewable market -alternative procurement options

Corporate consumers seeking to increase share of renewable power in their consumption mix have the option of using multiple short-term procurement routes like green power exchange, renewable energy certificates (RECs), I-RECs and green tariffs.

India Solar Rooftop Map | December 2023

India Solar Rooftop Map | December 2023

India Solar Rooftop Map is an info-graphic report providing a snapshot of rooftop solar market in India – capacity addition across states and consumer segments, market share of leading players and other key trends. Total rooftop solar capacity is estimated to have reached 14,484 MW by end of 2023. Total new installations in 2023 are estimated at 2,856 MW, up only 8% over previous year.

India Solar Map | December 2023

India Solar Map | December 2023

India Solar Map 2023 is an info-graphic report covering growth of utility scale solar sector – national and state-wise commissioned and pipeline capacity, leading market players and portfolio details of top 16 project developers. Capacity addition in 2023 fell 51% YOY to 5,924 MW taking total utility scale solar capacity to 59,840 MW. Total project pipeline stands at a record 74,161 MW.

India Corporate Renewable Brief | Q4 2023

India Corporate Renewable Brief | Q4 2023

This report provides an update on key trends and developments in the corporate renewable market including capacity addition, key players, policy & regulatory issuance, financing, PPA tariffs and other market trends.

India PV Module Intelligence Brief | Q4 2023

India PV Module Intelligence Brief | Q4 2023

This report captures quarterly trends in module demand and supply, import and domestic production volumes, supplier market shares, break-up by technology and rating, global market scenario, pricing trends across the value chain, key policy developments and market outlook.

India Solar Compass | Q4 2023

India Solar Compass | Q4 2023

This report provides a detailed update of all key sector developments and trends in the quarter – capacity addition, leading players, tenders and policy announcements, equipment prices, financial deals and other market developments. It also provides market outlook for the next two quarters.

To top